Stage-I
| Date | Event Description |
|---|---|
| 1937 | The Hirakud Scheme conceived by Er. M. Visveswaraya |
| 1945 | Agreement on unified development of the Mahanadi valley carried out between the Govt. of Odisha and Eastern states |
| 1946 | Foundation laying ceremony of the Hirakud Dam by Sri Hawthorne Lewis. I.C.S, Govt. of Odisha |
| 13th Apr 1948 | Foundation laid by Sri Jawaharlal Nehru |
| Feb 1949 | Construction of the Project Commenced |
| Aug 1948 - Dec 1949 | Preliminary design of Hirakud dam by International Engineering Co., Danver, USA |
| Mar 1952 | Appointment of Hirakud Control Board |
| Nov 1953 | The presentation of revised estimate amounting to Rs. 70.78 Crores to the Control Board during its 7th Meeting |
| Aug 1956 | Hirakud dam completed |
| 7th Sep 1956 | Irrigation water let out in the right side main canal. (Unit-3,24MW) |
| 18th Dec 1956 | First Hydro Power plant Commissioned |
| 13th Jan 1957 | The project inaugurated by Sri. Jawaharlal Nehru |
| 13th May 1957 | 24 MW, Unit-4 of Burla P.H. Commissioned |
| 11th Nov 1957 | 37.5 MW, Unit-2 of Burla P.H. Commissioned |
| 11th May 1957 | 37.5 MW, Unit-1 of Burla P.H. Commissioned |
Stage-II
| Date | Event Description |
|---|---|
| Jul 1956 | Chiplima scheme Sanctioned |
| Jan 1957 | Civil construction work started |
| Apr 1957 | Electrical construction work started |
| 19th Apr 1962 | 37.5 MW Generator No. 5 at Burla Power House Commissioned |
| Jul 1962 | Water let out in Power channel |
| 15th Jul 1962 | 24 MW Generator No. 1 at Chiplima Power House Commissioned |
| 26th Nov 1962 | 24 MW Generator No. 2 at Chilplima Power House Commissioned |
| 5th Aug 1963 | 37.5 MW Generator No. 6 at Burla PH Commissioned |
| 14th Sep 1963 | Inauguration of the Project by Dr. A.N. Khosla |
| 1st Feb 1964 | 24 MW Generator No. 3 at Chiplima Commissioned |
Stage-III
| Date | Event Description |
|---|---|
| Aug 1982 | Hirakud stage-III Project sanctioned by Planning Commission |
| Mar 1983 | Civil Construction Work Started |
| Nov 1986 | Civil Foundation Work Completed |
| Mar 1987 | Erection of Draft Tube Gate, Penstock Gate, Spiral Casing Completed |
| 13th Sep 1990 | 37.5 MW Generator No. 7 at Burla P.H Commissioned |