The important event of commissioning of 1st Stage and 2nd stage works are given below.

Commissioning of units

NameUnit-I Unit-II Unit-III Unit-IV
First spinning synchronised to grid 19.12.8729.03.88 24.01.90 03.07.92
Commercial15.03.88 14.04.88 10.02.90 22.07.92
Operation15.03.8816.04.88 10.02.90 12.01.93