OHPC Hydro Power Plant

Stage-I Work

The Stage-I of the Hydro Electric Power Station has two generating Units of 50 M.W. each with a firm power of 60 MW (Corresponding to a firm generation of 526 MU per year).

The Stage-I work also includes installation of penstock Gates, Penstock, Draft Tube Gates etc. for three more Units, covered under Stage-II work. The power house Auxiliaries, such as, two numbers of Electrical Overhead Travelling Cranes, Gantry Cranes for hosting the Draft Tube Gates / Penstock Gates / Stoplogs, Ventilation and Air Conditioning Systems, Passenger Lifts, Station Dewatering and Drainage System, Station Compressor System, Station D.C. System, Station Auxiliary Power Supply System etc. are also covered under Stage-I.

For the evacuation of power from the Station a 220 KV Switchyard, having 8 bays, i.e. 2 for the Generating Units, 1 for Station Transformer, 1 for bus coupler, 4 for outgoing feeders (Two to Rengali switchyard, one to kaniha Super Thermal Station and one to NALCO), has been provided under Stage-I.

A House Service Set of capacity 500 KW with a Francis turbine has been installed under Stage-I to provide start-up power in case of total power failure.

46% of the cost of the Dam has been apportioned to Power Generation. The Power Scheme estimated cost for Stage-I is as below :

The expenditure of Electrical works is Rs. 3566.82 Lakhs upto 31.3.92 Units-I & II have been commissioned and synchronised to Odisha Grid on 27.8.85 & 26.3.86 respectively. They are now in commercial operation.

Sl. No. Initial Rs. in Lakhs Last Revised Rs. in Lakhs
Cost of the Dam Apportioned to Power Generation (46%) 1932.007813.56
Power House Civil Works 330.00 2635.00
Electrical Works1270.683588.00
Total3532.68 14036.56

Stage-II Works

The Stage-II of the Power Station has three more generating Units (Unit Nos. III, IV & V) each of 50 MW Capacity. The secondary generation would be 225 MU (equivalent to annual average power of 25.68 MW).The administrative approval for Stage-II works was communicated by I&P Department, Govt. of Odisha on their letter no 26567 & 33407 dated 13.06.96.

For transmission of power of Stage-II Units three more bays have been provided in the existing 220 KV switchyard.

The power scheme estimated cost for Stage-II is as below

The erection works of Stage-II units started during the year 1987, Unit-III, Unit-IV & Unit-V have been commissioned and synchronised to Odisha Grid on 10.8.89, 19.3.90 and 14.8.92 respectively.

The total expenditure on dam Rs. 171,01,27,460/- up to March 1993 and power house works.

Sl. No.Initial Rs. in LakhsLast Revised Rs. in Lakhs
Power House Civil Works258.001122.00
Electrical Works3979.006274.00

Accessibility Adjustments

Content Adjustments

Decrease Font Size
Default Font Size
Increase Font Size
Highlight Titles
Text Magnifier

Color Adjustments

Light Contrast Theme
Dark Contrast Theme
High Contrast
Monochrome
Adjust Text Colors
High Saturation
Adjust Title Colors

Orientation Adjustments

Hide Images
Highlight Hover
Big Black Cursor
Big White Cursor