Stage-II Works
The Stage-II of the Power Station has three more generating Units (Unit Nos.III, IV & V) each of 50 MW capacity. The secondary generation would be 225 MU (equivalent to annual average power of 25.68 MW).The administrative approval for stage-II works was communicated by I&P Department, Govt. of Odisha on their letter no 26567 & 33407 dated 13.06.96.
For transmission of power of Stage-II Units three more bays have been provided in the existing 220 KV switchyard.
The power scheme estimated cost for stage-II is as below
The erection works of stage-II units started during the year 1987, Unit-III, Unit-IV & Unit-V have been commissioned and synchronised to Odisha Grid on 10.8.89, 19.3.90 and 14.8.92 respectively.
The total expenditure on dam Rs.171,01,27,460/- up to March 1993 and power house works.