Achievements for the FY 2024-25
- The Company has earned a profit of Rs.338.19 crore in the Financial Year 2024-25
- The Company paid dividend of Rs.101.46 Cr. to Government exchequer for the FY 2024-25.
Achievements for the FY 2022-23
- The generation from Rengali Hydro Electric Project, Rengali and Hirakud Hydro Electric Project, Burla crossed their respective design energy.
- OHPC supplied electricity to Odisha grid at a very low cost at OERC approved rate of 89.48 paisa per unit.
- After Renovation & Modernization work of Unit-1, BHEP Balimela started its commercial operation with effect from 15.04.2022.
- Inter-state clearance for the Upper Indravati Pumped Storage Project (4 x 150 MW) has been obtained from Director, Inter-state, New Delhi on 13.09.2022.
- Topographical survey report of Upper Kolab Pumped Stonage Project (2 x 160 MW) completed in May 2022.
- Forest Clearance for Geotechnical Investigation of Kharag Hydro Electric Project (63 MW) has been received from DFO on 24.12.2022 and 22.12.2022 respectively.
Achievements for the FY 2021-22
- OHPC played a key role in meeting the energy demand of the State during peak hours for grid stabilization.
- In the FY 2021-22 cumulative generation of Rengali HEP 865.277 MU and the power house has crossed the design energy generation target of 525MU.
- In the FY 2021-22 the cumulative generation of HHEP, Burla is 708.877 MU. Hence, the power house has crossed the design energy generation target of 684 MU.
- After Renovation, Modernization and Uprating works, Generating capacity of Unit-6 enhanced from 37.5 MW to 43.65 MW. Commercial operation of Unit-6 of HHЕР, Burla commenced w.e.f 02.11.2021.
- After Renovation, Modernization and Uprating works, Generating capacity of Unit-5 enhanced from 37.5 MW to 43.65 MW. Commercial operation of Unit-5 of HHEP, Burla commenced w.e.f 09.01.2022
- After Renovation & Modernization works, Commercial operation of Unit-2 of BHEP, Balimela commenced from Dt. 29.12.2021.
- OHPC has made a profit of Rs. 88.86 Cr. during the FY 2021-22.
Achievements for the FY 2019-20 (Till Nov-2019)
- The employees of OHPC Ltd. have contributed their one day salary i.e. Rs.27,85,667/- (Rupees Twenty Seven Lakhs Eighty Five Thousand Six Hundred Sixty Seven) only towards the Chief Minister’s Relief Fund to help the people affected by the recent Cyclone “FANI”.
- The company paid a dividend of Rs. 31.58 cr. to the Government of Odisha for the FY 2018-19
- OHPC has been felicitated with “Workers Education Award-2019” for excellence in learning and development activities by DattopantThengdi National Board of Workers Education and Development, Ministry of Labour and Employment, Govt. of India.
- Ongoing R & M work of CHEP ,Chiplima . Erection Activity Completed. Commissioning activity started. Overall Progress completed up to 95 %.
- Ongoing R & M work of HHEP, Burla. Overall Progress of Erection & Supply of Material is 68%.
- R & M work of Unit- 1& 2 of BHEP, Balimela. Design Engineering activity completed up to 65 %. Material supply increased to 70 % of Unit- 01 & 02. Erection activity in Turbine / Generator front is in progress. 220 kV Switch Yard Bay extension work is under progress.
- Upper Kolab Hydro Electricity project, Bariniput of OHPC has received the 10th Kalinga Safety Excellence Award- 2018 (Gold Winner) instituted by “Institute of Quality and Environmental Management Services”.
Achievements for the FY 2018-19
- Gross Energy Saleduring the year was 5880.604 MU against MoU target of 5478.28 MU.
- The company earned Profit Before Tax of Rs 227.31 crores and Profit After Tax of Rs. 144.39
- The company will pay a dividend of Rs. 18.65 cr. to the Government of Odisha for the FY 2017-18
- Work Order for preparation of Detailed Project Report of Balimela Pump Storage project was placed in favour of WAPCOS Limited.
- WAPCOS has submitted the Draft Detailed Project Report to develop proposed Upper Indravati Pump Storage Project.
- Progress in the R& M work of CHEP, Chiplima. Material supply increased to 99.5%. Erection activity completed up to 70 % . Rotor Building Completed.
- Progress in the R & M work of HHEP, Burla Overall progress of Erection & Supply of Material is 63%.
- R & M work of Unit- 1&2 of BHEP, Balimela ongoing and 40% Design works completed. Erection work of Unit- 1& 2 completed up to 15%.