The important event of commissioning of 1st Stage and 2nd stage works are given below.
Commissioning of units
| Name | Unit-I | Unit-II | Unit-III | Unit-IV |
|---|---|---|---|---|
| First spinning synchronised to grid | 19.12.87 | 29.03.88 | 24.01.90 | 03.07.92 |
| Commercial | 15.03.88 | 14.04.88 | 10.02.90 | 22.07.92 |
| Operation | 15.03.88 | 16.04.88 | 10.02.90 | 12.01.93 |