OHPC Hydro Power Dam
Event DescriptionDate
The Concreting of Power Plant was Commenced DuringMay 1969
Power House Concreting19th Nov 1969
The First Turbine Spiral Casing Installation was Started DuringAug 1971
Installation of the Generator was Commenced DuringMay 1972
Reservoir Filling15th Aug 1972
Water was Admitted into the Balimela Power Tunnel23rd May 1973
The First Turbine was put on Trial RunAt the End of May 1973.
First Unit was Commissioned14th Aug 1973
After R & M Commercial Operation of Unit I and II were StartedOn 15th Apr 2022 and 29th Dec 2021 Respectively